Construction Submittal Log Template for Excel: How to Build One

Build a construction submittal log template in Excel: the columns to include, status codes, formulas for overdue items, and when to move beyond a spreadsheet.

Docviro Team 10 min read
Construction Submittal Log Template for Excel: How to Build One

A construction submittal log is a spreadsheet that lists every shop drawing, product data sheet, sample and other submittal the specifications require. It then tracks each one from the subcontractor to the design team and back. A useful Excel template needs about a dozen core columns: submittal number, revision, spec section, description, type, responsible party, the key dates (required on site, sent for review, due back, returned), the reviewer's action, the current status, and who currently has the "ball in court."

You can build one in under an hour with an Excel Table, a few dropdown lists and three or four date formulas that flag late submissions and overdue reviews automatically. This guide gives you the column layout, the formulas, a status scheme you can copy, and the habits that keep the log trustworthy from preconstruction to closeout.

What a Submittal Log Is For

Submittals are how the contractor shows the design team exactly what will be installed before it is fabricated or ordered. The specifications, usually in a Division 01 section on submittal procedures, list what is required and how long the architect or engineer has to review it. The log answers three questions at any moment:

  • What is required? Every submittal called for in every spec section, so nothing is missed.
  • Where is it? With the subcontractor, with the general contractor, with the architect, or returned.
  • Is it going to hurt the schedule? Whether a late approval will push back procurement and installation.

The log is also a record. When a dispute comes up about whether a product was approved, or whether a review came back late, the log and the stamped submittals it points to are the evidence. That is why accuracy matters more than formatting.

The Columns Your Template Needs

Start with the columns below. You can add more, but resist the urge to track everything; each extra column is one more thing someone has to keep updated.

Column What goes in it Example
Submittal No. Unique ID tied to the spec section 08 71 00-003
Rev Revision number, starting at 0 1
Spec Section MasterFormat number and title 08 71 00 Door Hardware
Description What is being submitted Hardware schedule, Level 2
Type Shop drawing, product data, sample, test report, certificate, O&M, warranty Product data
Responsible Party Subcontractor or supplier ABC Doors
Required on Site Date material must be on site 2025-09-15
Lead Time (days) Fabrication and delivery time after approval 30
Review Days Review period allowed by the spec 10
Submit By Latest date to send for review (calculated) 2025-07-07
Received from Sub Date the GC received it 2025-06-30
Sent to A/E Date sent to the architect or engineer 2025-07-02
Due Back Date the review is due (calculated) 2025-07-16
Returned Date the review came back 2025-07-14
Action Reviewer's stamp Approved as Noted
Status Where the item stands now Closed
Ball in Court Who must act next GC
File Link Path or link to the submitted and returned PDFs link
Notes Short comments only Finish changed to US26D

If your projects use a separate reviewer such as a structural engineer or a commissioning agent, add a "Reviewer" column so you can filter by who is holding items.

Numbering Submittals and Revisions

The most common convention ties the number to the spec section, followed by a sequence number: 08 71 00-001, 08 71 00-002 and so on. This sorts naturally by section and makes it obvious which part of the specification each item answers.

For resubmittals, keep the original number and increase the revision: 08 71 00-003 Rev 0, then Rev 1, then Rev 2. Do not assign a new number to a resubmittal, or you lose the history of how many rounds an item took.

You have two options in Excel:

  1. One row per revision. Each round gets its own row with its own dates. This gives you accurate review times per round and is the better choice if you report on reviewer turnaround.
  2. One row per submittal, overwritten. Simpler to read, but you lose earlier dates unless you record them in Notes.

One row per revision is the more defensible approach. Filter on Status to hide superseded rows when you want a clean view.

Action Codes and Status: Keep Them Separate

A frequent mistake is using one column for both the reviewer's stamp and the overall status. They answer different questions.

Action is what the reviewer decided. Wording varies by firm and by contract, so copy the exact terms from the project's review stamp. Common ones are:

  • Approved (or No Exceptions Taken)
  • Approved as Noted (or Make Corrections Noted)
  • Revise and Resubmit
  • Rejected
  • For Record Only / Information Only

Status is where the item stands in your process:

  • Not Started
  • With Sub
  • GC Review
  • With A/E
  • Returned
  • Closed
  • Superseded

An item stamped "Revise and Resubmit" has a Returned status on that row, then a new revision row that starts at With Sub. Keeping the two columns separate lets you count how many items are stuck at the architect versus how many came back with problems.

Building the Template in Excel Step by Step

1. Set Up the Table

Enter your column headers in row 1, select the range and press Ctrl+T to format it as an Excel Table. Name the table Log (Table Design > Table Name). Tables extend formulas and formatting to new rows automatically and let you use readable structured references.

On a second sheet, list the project's non-working days in a single column and name that range Holidays. The date formulas below use it to skip holidays.

2. Add Dropdown Lists

Create a "Lists" sheet with your Type, Action and Status values. Then select the matching column in the log and use Data > Data Validation > List, pointing to each range. Dropdowns prevent the slow drift into "Approved," "approved," "APPR" and "OK" that breaks every filter and count.

3. Add the Date Formulas

Submit By works backward from when the material is needed:

=IF([@[Required on Site]]="","",WORKDAY([@[Required on Site]],-([@[Lead Time (days)]]+[@[Review Days]]),Holidays))

Enter lead time in working days. Suppliers often quote in weeks, so multiply weeks by 5. If you want a safety margin for a possible resubmittal, add a Buffer column and include it in the subtraction.

Due Back calculates when the review should return:

=IF([@[Sent to A/E]]="","",WORKDAY([@[Sent to A/E]],[@[Review Days]],Holidays))

Check the spec: some contracts count review time in calendar days, not working days. If yours does, replace WORKDAY with a simple addition.

Days Out shows how long the reviewer has held the item:

=IF([@[Sent to A/E]]="","",NETWORKDAYS([@[Sent to A/E]],IF([@Returned]="",TODAY(),[@Returned]),Holidays)-1)

Flag marks items that need attention:

=IF(AND([@[Sent to A/E]]<>"",[@Returned]="",TODAY()>[@[Due Back]]),"REVIEW OVERDUE",IF(AND([@[Sent to A/E]]="",[@[Submit By]]<>"",TODAY()>[@[Submit By]]),"SUBMIT LATE",""))

4. Add Conditional Formatting

Select the table body, then Home > Conditional Formatting > New Rule > Use a formula. Use a rule such as =$T2="REVIEW OVERDUE" (adjust the column letter to wherever Flag sits) with a red fill, and a second rule for "SUBMIT LATE" in amber. Keep it to two or three colors so the alerts stand out.

5. Build a Summary View

On a Dashboard sheet, use COUNTIFS for quick counts:

=COUNTIFS(Log[Status],"With A/E")
=COUNTIFS(Log[Flag],"REVIEW OVERDUE")
=COUNTIFS(Log[Action],"Revise and Resubmit")

A small pivot table by Responsible Party and Status is also useful for subcontractor meetings, since it shows each trade exactly what they owe.

Working Backward From the Schedule

The Submit By column is what turns a log into a planning tool. Populate Required on Site from the construction schedule early, ideally during preconstruction, and get real lead times from suppliers rather than guesses. Long-lead items such as switchgear, elevators, curtain wall and custom millwork are where a late submittal does the most damage, so sort by Submit By and review the top of the list in every weekly meeting.

When the schedule changes, update Required on Site. The Submit By and Flag columns recalculate on their own.

Habits That Keep the Log Accurate

A template is only as good as the discipline behind it.

  • Build the register from the specs, not memory. Go section by section and add a row for every required submittal before the first one arrives.
  • Assign one owner. One person updates the log. Others can read it.
  • Update the same day. Log dates when items move, not at the end of the week.
  • Record actual dates, not planned ones, in the Received, Sent and Returned columns.
  • Link every row to its files. Store the submitted package and the stamped return together, named with the submittal number and revision, for example 087100-003_R1_Returned.pdf.
  • Keep one master copy. Emailing the workbook creates competing versions within days.
  • Review it weekly with the project team and the trades.

Where a Spreadsheet Log Falls Short

Excel works well for a single project with a small team. Problems appear as projects grow or multiply:

  • The log and the files are separate. The spreadsheet says Approved as Noted, but the stamped PDF lives in someone's inbox or a shared drive folder that may not match.
  • Version confusion. Several copies of the workbook circulate, and nobody knows which is current.
  • No audit trail. Excel does not show who changed a date or a stamp, which weakens the log as evidence.
  • Manual handoffs. Every movement depends on someone emailing a PDF and remembering to update a cell.
  • Sharing with outside parties. Sending files to subs and design consultants by email attachment is hard to control and track.

For a broader look at organizing drawings, RFIs and contracts alongside submittals, see our guide to construction document management.

How Docviro Handles Submittals

Docviro is a general document management platform rather than a construction project management suite, but it covers the document side of the submittal process that a spreadsheet cannot.

  • Folders with permissions. Organize submittals by project and spec section, and control who can view or edit each folder.
  • Version history. Each resubmittal is saved as a new version of the same document, so Rev 0, Rev 1 and the stamped return stay together with a clear record. See version control.
  • Approval workflows. Route a submittal through GC review to the architect or engineer, assign reviewers and record each decision. See workflow automation.
  • Audit logs. Every upload, review and approval is recorded with a user and timestamp, which supports the log as a record.
  • Secure sharing with expiring links. Send packages to subcontractors and consultants without email attachments, and cut off access when the link expires.
  • Full-text search with OCR. Find text inside scanned, stamped PDFs, such as a product model number or a reviewer comment.
  • AI metadata extraction and summaries. Pull fields like spec section or manufacturer from documents and get a quick summary of long product data packages.
  • Retention rules. Keep closed-out project records for the period your contracts and policies require.

Many teams keep a slim Excel log for schedule planning and use Docviro as the single home for the files and approvals it points to. If you are designing the review steps themselves, our guide to creating approval workflows walks through the setup.

FAQ

What is the difference between a submittal log and a submittal register?

The terms are often used interchangeably. Where a distinction is made, the register is the list of everything the specifications require, built at the start of the project, while the log tracks the actual movement and review of each item. In practice, most teams keep both in one spreadsheet.

Who is responsible for maintaining the submittal log?

On most projects the general contractor maintains it, usually a project engineer or project coordinator. The contract documents, typically the general conditions and the Division 01 submittal section, set out each party's responsibilities. Subcontractors often keep their own logs, but the GC's log is the one used in project meetings.

How should I handle a submittal marked Revise and Resubmit?

Close out the current row with the returned date and action, then add a new row with the same submittal number and the next revision number. Status on the new row starts at With Sub, and the Due Back date resets when it goes back to the reviewer. This keeps an honest record of each review round.

Should review time be counted in working days or calendar days?

Follow the specification. Many contracts state the review period in working days, but some use calendar days. Use WORKDAY with a holiday list for working days, or simple date addition for calendar days.

When should we move beyond an Excel submittal log?

Consider it when several people need to update the log, when you run multiple projects at once, or when finding the right stamped PDF takes longer than it should. At that point, a document management system with version history, approval workflows and audit logs keeps the files and decisions in one place.

Topicsconstructionsubmittal logexcel templatesapproval workflowsdocument control