Free Construction Submittal Log Template + Approval Workflow

Copy this free construction submittal log template, learn what each column means, and follow a step-by-step approval workflow example from sub to architect.

Docviro Team 11 min read
Free Construction Submittal Log Template + Approval Workflow

A construction submittal log is a single register that tracks every shop drawing, product data sheet, sample and mockup. Each entry runs from the moment a subcontractor sends it to the moment the architect or engineer returns it with a review action. The free template below includes the columns that matter: submittal number, spec section, description, type, responsible party, revision, key dates, review action and who currently holds the ball. Copy it into a spreadsheet or your document system and you can start logging today.

The log only works if it sits inside a clear approval workflow. In that workflow, the subcontractor prepares the package and the general contractor reviews and stamps it. The design team then reviews it and returns an action, the GC distributes the result, and the sub releases material for fabrication only when that action allows it. Below you will find the template, a status code table, a full worked example for structural steel shop drawings, and the mistakes that most often lead to late materials and rework.

What a Submittal Log Is For

Submittals are how the contractor shows the design team exactly what will be built and installed before money is spent on fabrication. On projects that use CSI MasterFormat specifications, the rules usually sit in Division 01, Section 01 33 00 (Submittal Procedures), plus the submittal requirements listed in each technical section.

A well-kept log does four jobs:

  • Shows what is required. It lists every submittal the specs call for, so nothing is missed until the week material is needed.
  • Protects the schedule. Each item carries a need-by date worked back from installation and lead time.
  • Shows who is holding things up. A ball-in-court column makes it obvious whether the sub, the GC or the design team has the next move.
  • Creates a record. If there is a later dispute about an approved product or a substitution, the log and the stamped documents show what was submitted, when, and what the reviewer said.

The Free Construction Submittal Log Template

Copy these columns into Excel, Google Sheets or the metadata fields of your document system. Keep one row per submittal revision, or one row per submittal with a revision column, but pick one approach and stick to it.

Column What to enter Why it matters
Submittal No. Spec section plus sequence, e.g. 05 12 00-001 Unique ID that sorts by trade
Revision 0 for the first issue, then 1, 2, 3 Separates resubmittals from originals
Spec Section MasterFormat number and title Ties the item to contract requirements
Description Short plain-language title Makes the log readable at a glance
Type Shop drawing, product data, sample, mockup, calcs, warranty, O&M Different types need different reviewers
Subcontractor / Supplier Company responsible Tells you who to chase
Reviewer(s) Architect, structural engineer, MEP engineer, owner Some items need more than one consultant
Received from Sub Date Starts the GC review clock
Sent to Design Team Date Starts the reviewer's contractual clock
Due Back Sent date plus contract review period Lets you flag overdue reviews
Returned Date Ends the review cycle
Action Review stamp result (see codes below) Decides whether work can proceed
Ball in Court Sub, GC or Design Shows who owns the next step
Lead Time Fabrication and delivery time after approval Drives the need-by date
Required Submit By Latest date to submit and still meet the schedule Your early warning
Notes / Links Comments and a link to the file Keeps context in one place

Here is what a few rows look like once a project is underway:

No. Rev Spec Section Description Type Sub Sent to Design Due Back Action Ball in Court
05 12 00-001 1 05 12 00 Structural Steel Level 2 framing shop drawings Shop drawing Steel fabricator Day 18 Day 32 Pending Design
08 11 13-001 0 08 11 13 Hollow Metal Doors Door and frame product data Product data Door supplier Day 10 Day 24 Approved as noted Sub
09 65 13-002 0 09 65 13 Resilient Base Color samples Sample Flooring sub Day 12 Day 26 Revise and resubmit Sub

Numbering Convention

The spec section plus sequence format (for example 05 12 00-001) is widely used because it groups submittals by trade and makes the spec reference obvious. Add the revision as a separate column or a suffix such as 05 12 00-001.1. Never reuse a number for a different item, and never give a resubmittal a new base number. Otherwise the history of that item splits across two rows and nobody can follow it.

Building It in a Spreadsheet

A spreadsheet is fine for small projects. Add a formula for Due Back, conditional formatting for overdue items, and a filter on Ball in Court. If you want step-by-step formulas and formatting, see our guide on building a construction submittal log template in Excel.

Review Actions and Status Codes

Stamp wording varies by design firm, so use the terms your specification defines. The table below covers the most common actions and what each one means for the sub.

Action Typical meaning What happens next
No exceptions taken / Approved Reviewer found no issues within the scope of review Sub may proceed with fabrication or ordering
Approved as noted / Make corrections noted Acceptable if the marked corrections are made Sub proceeds and incorporates the notes; some specs also require a corrected copy for record
Revise and resubmit Not acceptable as submitted Sub revises and resubmits as the next revision; no fabrication
Rejected Does not meet the contract requirements Sub submits a compliant product or a formal substitution request
For record / Information only Filed without approval action Nothing to approve; keep in project records

Design review does not normally shift responsibility for meeting the contract documents onto the design team. Standard general conditions such as AIA A201 address shop drawings, product data and samples in Section 3.12. These conditions generally keep the contractor responsible for deviations unless the deviation was specifically pointed out and accepted. Read your own contract for the exact language.

Approval Workflow Example: Structural Steel Shop Drawings

This worked example follows one submittal through a full cycle, including a resubmittal. In this hypothetical project the specification gives the architect 14 calendar days per review.

  1. Sub prepares the package (Day 1). The steel fabricator's detailer produces Level 2 framing shop drawings and connection calculations. The fabricator sends them to the GC with a transmittal. The GC logs 05 12 00-001, Rev 0, with Received from Sub on Day 1 and Ball in Court set to GC.
  2. GC review (Days 1 to 4). The project engineer checks the drawings against the structural drawings and spec: member sizes, connection types, coordination with MEP openings. The GC applies its review stamp, which states that it has reviewed and coordinated the package. The log shows Sent to Design on Day 4, Due Back on Day 18, and Ball in Court set to Design.
  3. Design review (Days 4 to 16). The architect forwards the package to the structural engineer of record. The engineer marks two connections that need revision and returns the package with Revise and resubmit. The architect returns it to the GC on Day 16.
  4. GC distributes (Day 16). The GC logs the return date and action, sets Ball in Court to Sub, and sends the marked-up set to the fabricator the same day. Fabrication stays on hold.
  5. Sub resubmits (Day 21). The fabricator revises the connections and clouds the changes. The GC logs Rev 1 against the same number, reviews it, and sends it to the design team on Day 22. Due Back is now Day 36.
  6. Second review (Days 22 to 30). The engineer returns Rev 1 as Approved as noted, with one minor dimension correction. The architect returns it on Day 30.
  7. Release for fabrication (Day 30). The GC logs the action, sets Ball in Court to Sub, and distributes the stamped set. The fabricator incorporates the note and starts fabrication. The stamped Rev 1 becomes the controlling document and Rev 0 is kept as superseded history.

A few points make this workflow hold up:

  • One transmittal per submittal. Bundling unrelated items slows review and confuses the log.
  • Clouded changes on resubmittals. Reviewers should not have to re-check the whole set.
  • Same-day distribution. Every day a returned submittal sits in the GC's inbox comes out of the fabricator's schedule.
  • Clear superseded copies. Only the latest approved revision should be on site or in the shop. Strict version control prevents crews from building off Rev 0.

Working Back From the Need-By Date

The most useful column in the log is often Required Submit By. Calculate it like this:

Required Submit By = Installation start - Lead time - Design review period - GC review time - Buffer for one resubmittal

For example, suppose steel erection starts on a given date and fabrication plus delivery takes eight weeks. The design team has two weeks per review and the GC needs three working days. The submittal then has to go in roughly eleven weeks before erection, plus another review cycle if you assume one resubmittal. Long-lead items such as switchgear, elevators, curtain wall and custom doors usually drive the first submittals on a job. Ask suppliers for current lead times rather than relying on old numbers.

Common Submittal Log Mistakes

  • Starting the log late. Build the full register from the specs at the start of the job, not as packages trickle in.
  • No ball-in-court column. Without it, every overdue item becomes an argument about who was waiting on whom.
  • Tracking dates in email only. If the transmittal date lives in someone's inbox, the record disappears when that person leaves the project.
  • Mixing revisions. Logging a resubmittal as a new number, or overwriting Rev 0 data with Rev 1, breaks the audit trail.
  • Releasing on Revise and resubmit. Fabricating before an acceptable action is a costly gamble.
  • Files scattered across drives. The log says Approved, but nobody can find the stamped PDF. Keep files and log entries linked. Our guide to construction document management covers how to organize drawings, RFIs and contracts together.

How Docviro Handles Submittals

Docviro is a document management platform, not a scheduling tool, so it does not replace your project schedule. It gives the submittal documents and their approvals a single, controlled home.

  • Folders with permissions. Create a project folder with subfolders by spec division. Give subcontractors access only to their own trade folders, and give the design team access to what they review.
  • Metadata on each file. Store submittal number, spec section, revision, type and status as metadata, so you can search and filter submittals by these fields. AI metadata extraction can suggest values from a transmittal or cover sheet for you to confirm.
  • Approval workflows. Route each submittal through GC review and then design review, with assigned approvers and notifications at each step. See how routing works on the workflow automation page.
  • Version history. Rev 0, Rev 1 and later revisions stay attached to the same document, so the latest approved version is clear and earlier versions remain available.
  • Full-text search with OCR. Scanned stamps and marked-up drawings become searchable, which helps when you need to find every submittal that mentions a specific product.
  • Electronic signatures. Reviewers can sign approvals electronically. Each signature comes with a certificate of completion and a public verification page.
  • Secure sharing and audit logs. Send packages to outside consultants with expiring links. The audit log records who viewed, approved or downloaded each file.
  • Retention rules. Keep closed-out project records for the period your contracts and policies require.

FAQ

What is the difference between a submittal log and a submittal register?

Many teams use the terms interchangeably. Where they are distinguished, the register is the list of every submittal the specs require, usually prepared at the start of the project, and the log tracks the status and dates of each one as it moves through review. A single spreadsheet can serve as both if it includes the full list from day one.

Who maintains the submittal log?

On most projects the general contractor's project engineer or project manager owns the log, because the GC sits between the subcontractors and the design team. Some architects also keep their own log of what they have received and returned. Reconcile the two periodically so dates and actions match.

How long does submittal review take?

The review period is set by the contract, usually in Division 01 of the specifications, and it varies from project to project. Check whether it is stated in calendar or working days, and whether it restarts for resubmittals. Build that period into the Required Submit By date for every item.

Can submittals be approved with electronic signatures and stamps?

In the US, the ESIGN Act and state UETA laws generally give electronic signatures the same legal effect as handwritten ones. In the EU, eIDAS provides a similar framework. Your contract may still specify how submittals must be stamped or transmitted, so confirm the requirements with the owner and design team before switching to fully electronic approvals.

What is the difference between a submittal and an RFI?

A submittal shows the design team what the contractor intends to furnish or build, so they can confirm it meets the design intent. An RFI asks the design team to clarify something unclear or conflicting in the contract documents. Track them in separate logs, and do not use a submittal to ask design questions or an RFI to propose a substitution.

Topicsconstructionsubmittal logapproval workflowtemplatesproject documentation